Case studies

Case studies

Six projects where manufacturers and a supplier used DBR77 Digital Twin: a new production line, a plant expansion, a layout change, warehouse picking, an automation concept and a virtual showroom. The numbers come from the published case studies.

Projects

Six published projects

Each case study describes the plant, the task, the work done and the results.

Assembly benches of a straight line seen from a high angle in DBR77 Digital Twin 2.0Assembly benches of a straight line seen from a high angle in DBR77 Digital Twin 2.0

Car lamp manufacturer, southern Poland

Production line design: 6% more output per day

+6%

daily output compared with a linear layout

3

layout variants compared

A 2D plan of a hall zoomed in on stations and areas in DBR77 Digital Twin 2.0A 2D plan of a hall zoomed in on stations and areas in DBR77 Digital Twin 2.0

Car lamp manufacturer, southern Poland

Plant expansion: moving machines without stopping production

A plan that keeps production at the required level during the expansion.

A comparison of two layout variants in DBR77 Digital Twin 2.0: what changed and the key figuresA comparison of two layout variants in DBR77 Digital Twin 2.0: what changed and the key figures

Wooden furniture manufacturer

Layout optimization: 14% lower department costs

14%

lower department costs

PLN 300,000

less working capital

Racks of a hall in 3D in DBR77 Digital Twin 2.0Racks of a hall in 3D in DBR77 Digital Twin 2.0

Ventilation and cooling equipment manufacturer, Mazovia, Poland

Material retrieval from the warehouse: up to 60% less time

up to 60%

less picking time

1,000 s, 550 s, 200 s

simulated time: no optimization, island algorithm, sorting algorithm

A 2D plan zoomed in on racks and storage areas in DBR77 Digital Twin 2.0A 2D plan zoomed in on racks and storage areas in DBR77 Digital Twin 2.0

Plastic injection molding for household appliances, central Poland

Automation concept: an autonomous cart at the bottleneck

over 100%

higher efficiency at the bottleneck

90 s + 98 s

work and waiting at the first operator

A hall in 3D from another side with assembly benches and operators in DBR77 Digital Twin 2.0A hall in 3D from another side with assembly benches and operators in DBR77 Digital Twin 2.0

Industrial automation and robotics

Virtual showroom for Fanuc

Customers reach product information faster, and the showroom attracts more potential buyers.

Next step

Have a decision to test?

Describe your layout and the decision you are weighing. A DBR77 expert will show you how to test it on the digital twin, starting from the data you have.

Sign in or sign up at studio.dbr77.ai.