Car lamp manufacturer, southern Poland
Plant expansion: moving machines without stopping production
The same car lamp plant as in the production line case: 270 people on two shifts, a 28,000 m² building and a 12,000 m² warehouse. A new production hall was added to the plant.
Task
Plan the gradual move and set-up of machines so that production continues without a break. Also check the capacity of the intermediate storage areas and the continuity of internal deliveries.
Work
What was done
- Added the newly built area to the digital twin.
- Built the material flows with the process times of each task.
- Used process animation to choose the order of the moves.
- Analyzed production and material flow for each relocation option and chose the next process to move.
- Started the new area in Animation Mode and checked the assumptions.
Results
Results and benefits
Results
- A plan that keeps production at the required level during the expansion.
- The main question was where the storage areas between processes should be and how large they should be.
- The simulation showed that longer transport routes were the main cause of production losses.
Benefits
- An order of machine moves that runs processes in parallel.
- The final machine layout changed compared with the starting assumption.
- The management board watched the animations in VR goggles and decided faster on the order of the moves.
The facts and numbers come from the case study published on dbr77.com. Read the original
Video
The case study on video
The video loads from YouTube after you press play.
Product features used
Discuss a similar project